Construction Man-hour Norms

Jack Stud
DescriptionItemTradesman HoursLabourer Hours
100mm x 100mm (4 in x 4 in nominal)0.22 mhr/m - 0.0671 mhr/ft
Bearer
DescriptionItemTradesman HoursLabourer Hours
100mm x 75mm (4 in x 3 in nominal)0.22 mhr/m - 0.0671 mhr/ft
125mm x 100mm (5 in x 4 in nominal)0.24 mhr/m - 0.0732 mhr/ft
Joist
DescriptionItemTradesman HoursLabourer Hours
150mm x 50mm (6 in x 2 in nominal)0.20 mhr/m - 0.0610 mhr/ft
200mm x 50mm (8 in x 2 in nominal)0.21 mhr/m - 0.0640 mhr/ft
250mm x 50mm (10 in x 2 in nominal)0.22 mhr/m - 0.0671 mhr/ft
300mm x 50mm (12 in x 2 in nominal)0.22 mhr/m - 0.0671 mhr/ft
Solid Blocking
DescriptionItemTradesman HoursLabourer Hours
100mm x 50mm (4 in x 2 in nominal)0.17 mhr/m - 0.0518 mhr/ft
150mm x 50mm (6 in x 2 in nominal)0.23 mhr/m - 0.0701 mhr/ft
200mm x 50mm (8 in x 2 in nominal)0.25 mhr/m - 0.0762 mhr/ft
300mm x 50mm (12 in x 2 in nominal)0.32 mhr/m - 0.0975 mhr/ft
Beam
DescriptionItemTradesman HoursLabourer Hours
200mm x 50mm (8 in x 2 in nominal)0.23 mhr/m - 0.0701 mhr/ft
250mm x 50mm (10 in x 2 in nominal)0.28 mhr/m - 0.0853 mhr/ft
200mm x 100mm (8 in x 4 in nominal)0.29 mhr/m - 0.0884 mhr/ft
300mm x 100mm (12 in x 4 in nominal)0.36 mhr/m - 0.1097 mhr/ft