Task / DescriptionSlowAveFast
horizontal surfaces3.5 m²/hr - 37.67 sf/hr4.2 m²/hr - 45.21 sf/hr5.8 m²/hr - 62.43 sf/hr
vertical surfaces1.2 m²/hr - 12.92 sf/hr1.7 m²/hr - 18.30 sf/hr2.2 m²/hr - 23.68 sf/hr
Bituminous Brushed Application
Task / DescriptionSlowAveFast
2 coats4.8 m²/hr - 51.67 sf/hr5.0 m²/hr - 53.82 sf/hr6.3 m²/hr - 67.81 sf/hr
3 coats3.3 m²/hr - 35.52 sf/hr3.5 m²/hr - 37.67 sf/hr4.4 m²/hr - 47.36 sf/hr
Bituminous Sheets
Task / DescriptionSlowAveFast
horizontal surfaces3.8 m²/hr - 40.90 sf/hr4.0 m²/hr - 43.06 sf/hr4.8 m²/hr - 51.67 sf/hr
vertical surfaces3.3 m²/hr - 35.52 sf/hr3.5 m²/hr - 37.67 sf/hr4.2 m²/hr - 45.21 sf/hr
Polythene Sheets
Task / DescriptionSlowAveFast
horizontal surfaces20.0 m²/hr - 215.28 sf/hr
Bentonite Sheets
Task / DescriptionSlowAveFast
horizontal surfaces18.7 m²/hr - 201.27 sf/hr25.0 m²/hr - 269.10 sf/hr31.3 m²/hr - 336.95 sf/hr
vertical surfaces11.2 m²/hr - 120.56 sf/hr15.0 m²/hr - 161.46 sf/hr17.3 m²/hr - 186.23 sf/hr
Epoxy Based Application
Task / DescriptionSlowAveFast
1 coat75.0 m²/hr - 807.30 sf/hr
2 coat38.0 m²/hr - 408.93 sf/hr