Water Proofing
Planning Production Rates
Asphalt Coatings
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| horizontal surfaces | 3.5 m²/hr - 37.67 sf/hr | 4.2 m²/hr - 45.21 sf/hr | 5.8 m²/hr - 62.43 sf/hr |
| vertical surfaces | 1.2 m²/hr - 12.92 sf/hr | 1.7 m²/hr - 18.30 sf/hr | 2.2 m²/hr - 23.68 sf/hr |
Bituminous Brushed Application
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| 2 coats | 4.8 m²/hr - 51.67 sf/hr | 5.0 m²/hr - 53.82 sf/hr | 6.3 m²/hr - 67.81 sf/hr |
| 3 coats | 3.3 m²/hr - 35.52 sf/hr | 3.5 m²/hr - 37.67 sf/hr | 4.4 m²/hr - 47.36 sf/hr |
Bituminous Sheets
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| horizontal surfaces | 3.8 m²/hr - 40.90 sf/hr | 4.0 m²/hr - 43.06 sf/hr | 4.8 m²/hr - 51.67 sf/hr |
| vertical surfaces | 3.3 m²/hr - 35.52 sf/hr | 3.5 m²/hr - 37.67 sf/hr | 4.2 m²/hr - 45.21 sf/hr |
Polythene Sheets
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| horizontal surfaces | 20.0 m²/hr - 215.28 sf/hr |
Bentonite Sheets
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| horizontal surfaces | 18.7 m²/hr - 201.27 sf/hr | 25.0 m²/hr - 269.10 sf/hr | 31.3 m²/hr - 336.95 sf/hr |
| vertical surfaces | 11.2 m²/hr - 120.56 sf/hr | 15.0 m²/hr - 161.46 sf/hr | 17.3 m²/hr - 186.23 sf/hr |
Epoxy Based Application
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| 1 coat | 75.0 m²/hr - 807.30 sf/hr | ||
| 2 coat | 38.0 m²/hr - 408.93 sf/hr |
Last updated on