Restoration Works
Planning Production Rates
Façade Cleaning
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Water Jetting / Water Blasting | 25.0 m²/day - 269.10 ft²/day | ||
| Acid Etching | 9.0 m²/day - 96.88 ft²/day | ||
| Grit Blasting | 12.0 m²/day - 129.17 ft²/day |
Cladding Restoration
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Brickwork | 6.5 m²/day - 69.97 ft²/day | ||
| Stonework Courses | 20.0 m/day - 65.62 ft/day |
Last updated on