Stonework
Planning Production Rates
Stone Fixing to Metal Support Frame
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Fix 0.5m² Stones to Metal Support Frame | 5.6 m²/day - 60.28 ft²/day | 7.0 m²/day - 75.35 ft²/day | 7.8 m²/day - 83.96 ft²/day |
| Fix 0.5–0.75m² Stones to Metal Support Frame | 7.2 m²/day - 77.50 ft²/day | 9.0 m²/day - 96.88 ft²/day | 10.1 m²/day - 108.72 ft²/day |
| Fix 0.75–1.0m² Stones to Metal Support Frame | 6.9 m²/day - 74.27 ft²/day | 8.7 m²/day - 93.65 ft²/day | 9.7 m²/day - 104.41 ft²/day |
| Fix Complex Stonework to Metal Support Frame | 1.8 m²/day - 19.38 ft²/day |
Specialised Stone Fixing
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Fix Curved Stone Cladding | 6.9 m²/day - 74.27 ft²/day | 8.0 m²/day - 86.11 ft²/day | 9.2 m²/day - 99.03 ft²/day |
| Fix Stone Edge Beams / Window Reveals | 2.3 m²/day - 24.76 ft²/day | 3.2 m²/day - 34.44 ft²/day | |
| Fix Stone Soffits | 4.0 m²/day - 43.06 ft²/day |
Stone Flooring
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Stone Floors | 6.9 m²/day - 74.27 ft²/day | 10.4 m²/day - 111.94 ft²/day | 12.2 m²/day - 131.32 ft²/day |
Granite Wall Panels
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| First Fix | 1.3 m²/hr - 14.00 ft²/hr | ||
| Second Fix | 1.1 m²/hr - 11.84 ft²/hr |