Metal Decking
Planning and Estimating Production Rates
Metal Decking
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| large areas | 70.0 m²/day - 753.47 ft²/day | ||
| small or complicated | 28.0 m²/day - 301.39 ft²/day |
Titanium Roofs
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| Sheeted Roofs | 9.5 m²/day - 102.26 ft²/day |
Copper Roofs
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| flat work | 3.0 m²/day - 32.29 ft²/day | ||
| sloping work | 2.7 m²/day - 29.06 ft²/day |
Zinc Roofs
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| flat work | 2.4 m²/day - 25.83 ft²/day | ||
| sloping work | 2.1 m²/day - 22.60 ft²/day |
Aluminium Roofs
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| flat work | 2.8 m²/day - 30.14 ft²/day | ||
| sloping work | 1.9 m²/day - 20.45 ft²/day |
Lead Roofs
| Task / Description | Slow | Ave | Fast |
|---|---|---|---|
| flat work | 2.5 m²/day - 26.91 ft²/day | ||
| sloping work | 2.1 m²/day - 22.60 ft²/day | ||
| dormer cheeks | 1.3 m²/day - 13.99 ft²/day | ||
| flat gutters | 88.0 m/day - 288.71 ft/day | ||
| flat copings | 76.0 m/day - 249.34 ft/day | ||
| stepped gutters | 3.5 m/day - 11.48 ft/day | ||
| shaped copings | 3.3 m/day - 10.83 ft/day | ||
| cover step flashings | 3.2 m/day - 10.50 ft/day | ||
| rooflight flashings | 0.8 no/day | ||
| domed roof coverings | 0.7 m²/day - 7.53 ft²/day |