Skip to Content
Production RatesBuilding ConstantsRoof Coverings and FramesMetal Decking

Metal Decking

Planning and Estimating Production Rates

Metal Decking
Task / DescriptionSlowAveFast
large areas70.0 m²/day - 753.47 ft²/day
small or complicated28.0 m²/day - 301.39 ft²/day
Titanium Roofs
Task / DescriptionSlowAveFast
Sheeted Roofs9.5 m²/day - 102.26 ft²/day
Copper Roofs
Task / DescriptionSlowAveFast
flat work3.0 m²/day - 32.29 ft²/day
sloping work2.7 m²/day - 29.06 ft²/day
Zinc Roofs
Task / DescriptionSlowAveFast
flat work2.4 m²/day - 25.83 ft²/day
sloping work2.1 m²/day - 22.60 ft²/day
Aluminium Roofs
Task / DescriptionSlowAveFast
flat work2.8 m²/day - 30.14 ft²/day
sloping work1.9 m²/day - 20.45 ft²/day
Lead Roofs
Task / DescriptionSlowAveFast
flat work2.5 m²/day - 26.91 ft²/day
sloping work2.1 m²/day - 22.60 ft²/day
dormer cheeks1.3 m²/day - 13.99 ft²/day
flat gutters88.0 m/day - 288.71 ft/day
flat copings76.0 m/day - 249.34 ft/day
stepped gutters3.5 m/day - 11.48 ft/day
shaped copings3.3 m/day - 10.83 ft/day
cover step flashings3.2 m/day - 10.50 ft/day
rooflight flashings0.8 no/day
domed roof coverings0.7 m²/day - 7.53 ft²/day
Last updated on