Timber Frames

Construction Man-hour Norms

Ceiling Joist
ItemDescriptionTradesman HoursLabourer Hours
100mm x 50mm (4 in x 2 in)0.20 mhr/m - 0.06 mhr/ft
150mm x 50mm (6 in x 2 in)0.20 mhr/m - 0.06 mhr/ft
Ceiling Dwang
ItemDescriptionTradesman HoursLabourer Hours
100mm x 50mm (4 in x 2 in)0.21 mhr/m - 0.06 mhr/ft
Ceiling Strapping
ItemDescriptionTradesman HoursLabourer Hours
50mm x 25mm (2 in x 1 in)0.08 mhr/m - 0.02 mhr/ft
100mm x 25mm (4 in x 1 in)0.10 mhr/m - 0.03 mhr/ft
Rafter
ItemDescriptionTradesman HoursLabourer Hours
100mm x 50mm (4 in x 2 in)0.18 mhr/m - 0.05 mhr/ft
150mm x 50mm (6 in x 2 in)0.20 mhr/m - 0.06 mhr/ft
200mm x 50mm (8 in x 2 in)0.22 mhr/m - 0.07 mhr/ft
Collar Tie
ItemDescriptionTradesman HoursLabourer Hours
150mm x 25mm (6 in x 1 in)0.17 mhr/m - 0.05 mhr/ft
Strut and Brace
ItemDescriptionTradesman HoursLabourer Hours
100mm x 50mm (4 in x 2 in)0.12 mhr/m - 0.04 mhr/ft
100mm x 75mm (4 in x 3 in)0.22 mhr/m - 0.07 mhr/ft
Purlin
ItemDescriptionTradesman HoursLabourer Hours
75mm x 50mm (3 in x 2 in)0.12 mhr/m - 0.04 mhr/ft
100mm x 50mm (4 in x 2 in)0.15 mhr/m - 0.05 mhr/ft
150mm x 50mm (6 in x 2 in)0.17 mhr/m - 0.05 mhr/ft
200mm x 50mm (8 in x 2 in)0.20 mhr/m - 0.06 mhr/ft
Eaves Framing
ItemDescriptionTradesman HoursLabourer Hours
75mm x 50mm (3 in x 2 in)0.18 mhr/m - 0.05 mhr/ft
100mm x 50mm (4 in x 2 in)0.20 mhr/m - 0.06 mhr/ft
Fascia
ItemDescriptionTradesman HoursLabourer Hours
100mm x 50mm (4 in x 2 in)0.17 mhr/m - 0.05 mhr/ft
150mm x 50mm (6 in x 2 in)0.20 mhr/m - 0.06 mhr/ft
Ridge Board
ItemDescriptionTradesman HoursLabourer Hours
150mm x 25mm (6 in x 1 in)0.20 mhr/m - 0.06 mhr/ft
200mm x 25mm (8 in x 1 in)0.22 mhr/m - 0.07 mhr/ft
100mm x 50mm (4 in x 2 in)0.17 mhr/m - 0.05 mhr/ft
Valley Board
ItemDescriptionTradesman HoursLabourer Hours
150mm x 25mm (6 in x 1 in)0.18 mhr/m - 0.05 mhr/ft
200mm x 25mm (8 in x 1 in)0.20 mhr/m - 0.06 mhr/ft
150mm x 50mm (6 in x 2 in)0.16 mhr/m - 0.05 mhr/ft
200mm x 50mm (8 in x 2 in)0.21 mhr/m - 0.06 mhr/ft
Beams and Lintels
ItemDescriptionTradesman HoursLabourer Hours
200mm x 50mm (8 in x 2 in)0.27 mhr/m - 0.08 mhr/ft
300mm x 75mm (12 in x 3 in)0.34 mhr/m - 0.10 mhr/ft
200mm x 100mm (8 in x 4 in)0.34 mhr/m - 0.10 mhr/ft
300mm x 100mm (12 in x 4 in)0.45 mhr/m - 0.14 mhr/ft
Posts
ItemDescriptionTradesman HoursLabourer Hours
100mm x 100mm (4 in x 4 in)0.28 mhr/m - 0.09 mhr/ft
Prefabricated Roof Trusses
ItemDescriptionTradesman HoursLabourer Hours
Erection only6m span (20 ft span)1.50 mhr/No
9m span (30 ft span)2.00 mhr/No
12m span (40 ft span)3.00 mhr/No

Planning Production Rates

Basic Components
Task / DescriptionSlowAveFast
Roof Trusses1.3 no/hr - 1.3 no/hr
Wall Plates2.7 m/hr - 8.86 ft/hr
Roof Rafters1.2 m/hr - 3.94 ft/hr
Ceiling Joists32.1 m/hr - 105.31 ft/hr
Roof Carcass - Common Rafters
Task / DescriptionSlowAveFast
under 3m18.220.0 no/hr - 20.0 no/hr21.7
3-6m13.316.6 no/hr - 16.6 no/hr18.2
over 6m14.115.6 no/hr - 15.6 no/hr16.1
Roof Carcass - Jack Rafters
Task / DescriptionSlowAveFast
under 3m18.820.1 no/hr - 20.1 no/hr21.7
3-6m10.416.1 no/hr - 16.1 no/hr16.6
Roof Carcass - Purlins
Task / DescriptionSlowAveFast
under 3m5.15.4 no/hr - 5.4 no/hr5.8
3-6m4.34.8 no/hr - 4.8 no/hr5.1
over 6m3.54.3 no/hr - 4.3 no/hr4.6
Roof Carcass - Binders
Task / DescriptionSlowAveFast
under 3m5.76.6 no/hr - 6.6 no/hr7.6
3-6m2.12.3 no/hr - 2.3 no/hr2.5
over 6m1.31.5 no/hr - 1.5 no/hr1.6
Roof Carcass - Other Components
Task / DescriptionSlowAveFast
Hangers, under 3m8.29.0 no/hr - 9.0 no/hr9.6
Collars under 3m7.68.0 no/hr - 8.0 no/hr9.1
Collars 3-m6.57.4 no/hr - 7.4 no/hr8.3
Ridge Boards under 3m12.013.1 no/hr - 13.1 no/hr15.3
Cut Rafter Feet to line142.0166.0 no/hr - 166.0 no/hr175.0
Roof Soffits
Task / DescriptionSlowAveFast
Softwood, nailed9.2 m/hr - 30.18 ft/hr
Softwood, screwed3.9 m/hr - 12.80 ft/hr
Asbestos, under 300mm nailed9.1 m/hr - 29.86 ft/hr
Asbestos, under 300mm screwed3.8 m/hr - 12.47 ft/hr
Asbestos, over 300mm nailed3.5 m/hr - 11.48 ft/hr
Asbestos, over 300mm screwed1.3 m/hr - 4.27 ft/hr
Roof Facia Panels
Task / DescriptionSlowAveFast
Softwood5.17.2 m/hr - 23.62 ft/hr9.3
Asbestos1.32.5 m/hr - 8.20 ft/hr3.9
Roof Facia Panel Studding
Task / DescriptionSlowAveFast
nailed7.38.1 m/hr - 26.57 ft/hr9.0
screwed4.65.2 m/hr - 17.06 ft/hr5.8
bolted to beams5.45.9 m/hr - 19.36 ft/hr6.6
Roof Works - Miscellaneous
Task / DescriptionSlowAveFast
Fix Herringbone Strutting5.1 m/hr - 16.73 ft/hr
Fix Firing Strips25.0 m/hr - 82.02 ft/hr
Fix Drip/Tilt Filleting20.5 m/hr - 67.26 ft/hr
Last updated on