Concrete Placement Man-hour Norms

Unreinforced Readymix – Placed In
DescriptionTasksTradesman HoursLabourer Hours
Blinding layer 50mm (2 in) thick2.20 mhr/m3 - 2.88 mhr/yd3
Column and pier foundations1.20 mhr/m3 - 1.57 mhr/yd3
Strip footings1.30 mhr/m3 - 1.70 mhr/yd3
Reinforced Readymix – Placed In
DescriptionTasksTradesman HoursLabourer Hours
Column and pier foundations1.50 mhr/m3 - 1.96 mhr/yd3
Strip footings1.60 mhr/m3 - 2.09 mhr/yd3
Slabs and thickenings on fill1.75 mhr/m3 - 2.29 mhr/yd3
Suspended slabs 150/300mm (6/12 in) thick2.00 mhr/m3 - 2.62 mhr/yd3
Walls 150/300mm (6/12 in) thick2.00 mhr/m3 - 2.62 mhr/yd3
Columns2.90 mhr/m3 - 3.79 mhr/yd3
Attached beams2.25 mhr/m3 - 2.94 mhr/yd3
Isolated beams3.00 mhr/m3 - 3.92 mhr/yd3
Stairs and landings3.90 mhr/m3 - 5.10 mhr/yd3

Concrete Placement Planning Production Rates

Pump Placement
Task / DescriptionSlowAveFast
Lorry-based pump30.0 m³/hr - 39.24 yd³/hr40.0 m³/hr - 52.32 yd³/hr50.0 m³/hr - 65.40 yd³/hr
Hollorib Decking
Task / DescriptionSlowAveFast
Concrete topping85.0 m²/hr - 101.66 yd²/hr100.0 m²/hr - 119.59 yd²/hr120.0 m²/hr - 143.51 yd²/hr
Concrete topping incl. PowerFloat40.0 m²/hr - 47.84 yd²/hr50.0 m²/hr - 59.80 yd²/hr70.0 m²/hr - 83.71 yd²/hr
Wheelbarrow Placement
Task / DescriptionSlowAveFast
Over 1–10m2.1 m³/hr - 2.75 yd³/hr2.3 m³/hr - 3.01 yd³/hr2.5 m³/hr - 3.27 yd³/hr
Over 10–20m1.5 m³/hr - 1.96 yd³/hr1.8 m³/hr - 2.35 yd³/hr2.1 m³/hr - 2.75 yd³/hr
Over 20–50m0.8 m³/hr - 1.05 yd³/hr1.1 m³/hr - 1.44 yd³/hr1.5 m³/hr - 1.96 yd³/hr
Direct From Readymix Lorry
Task / DescriptionSlowAveFast
Mass fill2.8 m³/hr - 3.66 yd³/hr3.1 m³/hr - 4.05 yd³/hr3.3 m³/hr - 4.32 yd³/hr
50mm blinding-1.3 m³/hr - 1.70 yd³/hr1.6 m³/hr - 2.09 yd³/hr
Ground beams1.5 m³/hr - 1.96 yd³/hr-1.7 m³/hr - 2.22 yd³/hr
Pile caps1.0 m³/hr - 1.31 yd³/hr1.5 m³/hr - 1.96 yd³/hr2.3 m³/hr - 3.01 yd³/hr
Duct walls-0.8 m³/hr - 1.05 yd³/hr1.1 m³/hr - 1.44 yd³/hr
Stub columns-0.4 m³/hr - 0.52 yd³/hr0.6 m³/hr - 0.78 yd³/hr
Ground slab2.1 m³/hr - 2.75 yd³/hr2.3 m³/hr - 3.01 yd³/hr2.6 m³/hr - 3.40 yd³/hr
Drains bed & cover-0.9 m³/hr - 1.18 yd³/hr1.0 m³/hr - 1.31 yd³/hr
From Tower Crane
Task / DescriptionSlowAveFast
Pile caps1.2 m³/hr - 1.57 yd³/hr1.4 m³/hr - 1.83 yd³/hr1.6 m³/hr - 2.09 yd³/hr
Mass fill4.0 m³/hr - 5.23 yd³/hr4.5 m³/hr - 5.89 yd³/hr5.5 m³/hr - 7.20 yd³/hr
Slabs under 150mm thick0.9 m³/hr - 1.18 yd³/hr1.3 m³/hr - 1.70 yd³/hr1.7 m³/hr - 2.22 yd³/hr
Slabs over 150mm thick1.2 m³/hr - 1.57 yd³/hr1.5 m³/hr - 1.96 yd³/hr1.8 m³/hr - 2.35 yd³/hr
Trough / coffered slabs0.9 m³/hr - 1.18 yd³/hr1.1 m³/hr - 1.44 yd³/hr1.2 m³/hr - 1.57 yd³/hr
Stairs and landings0.6 m³/hr - 0.78 yd³/hr0.7 m³/hr - 0.91 yd³/hr0.9 m³/hr - 1.18 yd³/hr
Blinding0.8 m³/hr - 1.05 yd³/hr1.0 m³/hr - 1.31 yd³/hr1.1 m³/hr - 1.44 yd³/hr
Beams under 150mm thick0.5 m³/hr - 0.65 yd³/hr0.6 m³/hr - 0.78 yd³/hr0.8 m³/hr - 1.05 yd³/hr
Beams over 150mm thick0.6 m³/hr - 0.78 yd³/hr0.8 m³/hr - 1.05 yd³/hr1.0 m³/hr - 1.31 yd³/hr
Walls0.6 m³/hr - 0.78 yd³/hr1.1 m³/hr - 1.44 yd³/hr1.5 m³/hr - 1.96 yd³/hr
Columns0.4 m³/hr - 0.52 yd³/hr0.5 m³/hr - 0.65 yd³/hr0.6 m³/hr - 0.78 yd³/hr