Production RatesConcrete WorkFormworkScaffolding

Scaffolding

Planning Production Rates

Metal KwikStage
Task / DescriptionSlowAveFast
5 Boards with 2m lifts11.1 m run/hr - 36.42 ft run/hr11.9 m run/hr - 39.04 ft run/hr12.5 m run/hr - 41.01 ft run/hr
5 Boards with 3m lifts9.1 m run/hr - 29.86 ft run/hr10.0 m run/hr - 32.81 ft run/hr10.5 m run/hr - 34.45 ft run/hr
House Scaffold with 3 lifts2.8 m run/hr - 9.19 ft run/hr3.2 m run/hr - 10.50 ft run/hr3.8 m run/hr - 12.47 ft run/hr
Metal Tube and Fittings
Task / DescriptionSlowAveFast
5–6 Boards wide3.2 m run/hr - 10.50 ft run/hr3.7 m run/hr - 12.14 ft run/hr4.6 m run/hr - 15.09 ft run/hr
Tube and Fitting Platforms
Task / DescriptionSlowAveFast
50–250m³10.6 m³/hr - 13.87 yd³/hr12.5 m³/hr - 16.35 yd³/hr18.5 m³/hr - 24.20 yd³/hr
250–1000m³18.5 m³/hr - 24.20 yd³/hr22.5 m³/hr - 29.43 yd³/hr24.5 m³/hr - 32.05 yd³/hr
over 1000m³24.5 m³/hr - 32.05 yd³/hr30.0 m³/hr - 39.24 yd³/hr33.5 m³/hr - 43.82 yd³/hr
striking-200.0 % x erect-