Expansion Joint
Construction Man-hour Norms
Keyed Construction Joint
| Description | Item | Tradesman Hours | Labourer Hours |
|---|---|---|---|
| 150mm (6 in) slab | 0.30 mhr/m - 0.091 mhr/ft | ||
| 300mm (12 in) slab | 0.35 mhr/m - 0.107 mhr/ft |
Expansion Joint
| Description | Item | Tradesman Hours | Labourer Hours |
|---|---|---|---|
| 150mm (6 in) slab | 0.50 mhr/m - 0.152 mhr/ft | ||
| 300mm (12 in) slab | 0.60 mhr/m - 0.183 mhr/ft | ||
| 150mm (6 in) wall | 0.60 mhr/m - 0.183 mhr/ft | ||
| 300mm (12 in) wall | 0.70 mhr/m - 0.213 mhr/ft |
Last updated on