Skip to Content
Production RatesConcrete WorkJointsExpansion Joint

Expansion Joint

Construction Man-hour Norms

Keyed Construction Joint
DescriptionItemTradesman HoursLabourer Hours
150mm (6 in) slab0.30 mhr/m - 0.091 mhr/ft
300mm (12 in) slab0.35 mhr/m - 0.107 mhr/ft
Expansion Joint
DescriptionItemTradesman HoursLabourer Hours
150mm (6 in) slab0.50 mhr/m - 0.152 mhr/ft
300mm (12 in) slab0.60 mhr/m - 0.183 mhr/ft
150mm (6 in) wall0.60 mhr/m - 0.183 mhr/ft
300mm (12 in) wall0.70 mhr/m - 0.213 mhr/ft