Demolition – Estimating Man-hour Norms

Floors

DescriptionStructureTradesman HoursLabourer Hours
Remove vinyl floor tiles or carpet0.2 mhr/m² – 0.019 mhr/ft²
Break up and remove concrete floor topping
100mm thick1.00 mhr/m² – 0.093 mhr/ft²
150mm thick1.50 mhr/m² – 0.139 mhr/ft²
Scabble concrete to receive new screed0.2 mhr/m² – 0.019 mhr/ft²

Walls

DescriptionStructureTradesman HoursLabourer Hours
Demolish single skinned masonry wall0.5 mhr/m² – 0.046 mhr/ft²
Demolish timber framed partly glazed plasterboard wall0.3 mhr/m² – 0.028 mhr/ft²
Remove ceramic wall tiles on solid plaster, make good to receive paint1.00 mhr/m² – 0.093 mhr/ft²
Cut and form opening in single skin masonry wall for single door, including teething/bonding & making good to render7.00 mhr/No – 7.00 mhr/Ea

Roofing / Ceilings

DescriptionStructureTradesman HoursLabourer Hours
Take down suspended ceiling system0.3 mhr/m² – 0.028 mhr/ft²
Remove asphalt roofing, make good1.00 mhr/m² – 0.093 mhr/ft²

Demolition – Planning Production Rates

Weight
Task / DescriptionSlowAveFast
Structural Steel-2.5 Tonnes/m³ – 2.11 Tons/yd³-
Remove & Cart away
Task / DescriptionSlowAveFast
Ceramic Wall Tiles2.0 m²/hr – 21.53 ft²/hr2.5 m²/hr – 26.91 ft²/hr3.4 m²/hr – 36.60 ft²/hr
Wallpaper, 1 layer-8.7 m²/hr – 93.55 ft²/hr-
Wallpaper, 2 layers-7.1 m²/hr – 76.43 ft²/hr-
Wallpaper, 3 layers-5.7 m²/hr – 61.35 ft²/hr-
Lathe and Plaster Ceilings3.2 m²/hr – 34.44 ft²/hr4.6 m²/hr – 49.51 ft²/hr5.0 m²/hr – 53.82 ft²/hr
Plaster to Walls2.1 m²/hr – 22.60 ft²/hr3.1 m²/hr – 33.37 ft²/hr5.9 m²/hr – 63.51 ft²/hr
External Render-3.9 m²/hr – 41.98 ft²/hr-
Floor Screed-3.2 m²/hr – 34.44 ft²/hr-
Concrete Paving-4.0 m²/hr – 43.06 ft²/hr-
Brickwork Walls, 1.0 brick thick-1.3 m²/hr – 14.00 ft²/hr-
Brickwork Walls, 0.5 brick thick-2.6 m²/hr – 27.99 ft²/hr-
Brickwork Walls, Sand/Lime Mortar-1.8 hrs/100-
Fireplace and Hearth-1.9 hrs/no-
Floor Boards-6.2 m²/hr – 66.74 ft²/hr-
Skirting, Architrave, Dado rail etc-16.5 m/hr – 54.14 ft/hr-
Staircase-7.3 hrs/no-
Windows 0–1m²-0.6 hrs/no-
Windows 1–2m²-0.8 hrs/no-
Windows 2–3m²-0.9 hrs/no-
Doors-0.3 hrs/no-
Door Frame-0.1 hrs/no-
Floor and Ceiling Joists-1.1 hrs/m – 0.34 hrs/ft-
Wall Plates-3.9 hrs/m – 1.19 hrs/ft-
Iron Bath-1.4 hrs/no-
Wash Basin / Sink-0.8 hrs/no-
Pipework incl. brackets-6.1 m/hr – 20.01 ft/hr-