Backfilling & Compaction

Planning and Estimating Production Rates

Deep Vibroflotation
Task / DescriptionSlowAveFast
Deep Vibroflot, 3m centres330.0 m³/hr - 431.62 yd³/hr380.0 m³/hr - 497.02 yd³/hr465.0 m³/hr - 608.29 yd³/hr
Vibro-Rolling
Task / DescriptionSlowAveFast
Sand28.5 m²/hr - 34.09 yd²/hr31.2 m²/hr - 37.28 yd²/hr45.2 m²/hr - 54.06 yd²/hr
Soil-58.8 m²/hr - 70.33 yd²/hr-
Clay-55.6 m²/hr - 66.45 yd²/hr-
Hardcore-38.4 m²/hr - 45.93 yd²/hr-
Ash-57.8 m²/hr - 69.13 yd²/hr-