Skip to Content
Production RatesFoundationPiling ProductivitiesPiling Productivities

Piling Productivities

Foundation and Piling Production Rates

Bored PilesCFA Bored PilesDriven H Piles
AdvantagesBored pile are used to support multi-story building or bridges which can producing heavy vertical loadsThey are quick to install and have no requirement for temporary or permanent casingsDriven piles are driven to a set in variable site conditions to achieve uniform minimum capacity with high reliability
MethodologyPile drilled / soil removed and replaced with reinforced concreteAuger drilled into ground and replaced with concrete as the auger is removedSteel section driven into the ground
Design — Effect on adjacent groundNo displacement of the soil but the potential for relaxation / softening adjacent ground, dependant upon the soil and bore support usedTypically no displacement with good construction controls. Localised densification of loose non-cohesive soils.Small cross sectional area and hence minimal soil displacement or potential improvement
Design — Typical size ranges450-2500mm diameter450 – 1200 mm diameter depths up to 32m150 – 350 UC’s, UBPs
Design — Capacity - Shaft frictionMediumMediumMedium
Design — Capacity - End bearingVery high with enlarged baseMediumHigh
Design — Capacity - StructuralVery high structural capacity and stiffness achievableCage insertion can limit tensile and flexural capacity at depthDriving stresses often govern the steel section required
Design — DurabilityConventional concrete in the ground design. Permanent liner in highly aggressive conditionsConventional concrete in the ground designSacrificial thickness of steel above low groundwater level
Construction — Typical / PlantHydraulic or crane mounted piling rig, handling crane, casing, vibro with powerpack and / or drilling support fluid plantHydraulic piling rig, concrete pump and possible handling craneCrane, vibro hammer or hydraulic hammer with powerpack or drop hammer and leaders or guide frame
Construction — Piling productivity16m deep - 600dia @ 2No/day in soft material including a 3m soft rock socket depth. Detailed production rates16m deep - 600dia @ 11No/day in soft material including a 3m soft rock socket depth16m deep - 350 UC’s @ 22No/day in soft material
Construction — Material to PlantConcrete, reinforcement cages and method dependant materialConcrete and reinforcement cagesSteel sections
Construction — Materials storageCasing and cage lay down areaCage lay down areaH pile lay down area
Construction — NoiseMachine only unless driven casingMachine onlyYes, if vibro used hammer used to obtain pile set
Construction — VibrationNo, unless driven casing usedNoYes
Construction — Spoil100% Nett volume100% Nett volumeNone
Construction - OtherPlunged columns can be placed into the top of the pile to structural positional tolerancesFast installation process with real time monitoring systems for construction control and recordsFull strength welded splice used at connections. Predrilling can be used to overcome obstructions
Driven Tubes PilesPrecast Concrete PilesVibro replacement
AdvantagesThey are ideally suited for marine and other near shore applications with a very high end bearing capabilityPrecast driven piles can be environmentally friendly when construct temporary trestles in wetlandStone piles are a very effective technique, for resolving issues with liquefiable soils, that fall within the typical grain size range
MethodologyTube driven using external or internal hammer and filled with reinforced concretePre cast section driven into the groundSoil displaced or removed and replaced with stone
Design — Effect on adjacent groundLarge displacement of plugged tubes resulting in densification of non-cohesive soils and enhanced capacityLarge displacement resulting in densification of non-cohesive soils and enhanced capacityLarge displacement with densification of non-cohesive soils surrounding the stone column which enhances the capacity
Design — Typical size ranges350 – 750 mm diameter250 – 600 mm square600 – 1200 mm diameter
Design — Capacity - Shaft frictionMediumMediumLow
Design — Capacity - End bearingVery highVery HighLow
Design — Capacity - StructuralTubes can be reinforced concrete filled to enhance capacityLifting, driving and jointing can limit capacityStone quality & confinement in the soil limit the capacity
Design — DurabilitySacrificial thickness of steel and internal reinforced concreteConventional concrete in the ground design. Review potential corrosion at jointsWeathering / degradation of stone typically not an issue
Construction — Typical / PlantCrane, vibro hammer or hydraulic hammer with powerpack or drop hammer, leaders or guide frameCrane, hydraulic hammer with powerpack or drop hammer, leaders or guide frameCrane, vibro probe with power pack, water pumps, compressor and front loader
Construction — Piling productivity16m deep - 600mm Dia piles @ 22No/day16m deep - 300mm square piles @ 20No/day12m deep @ 6No/day in soft material
Construction — Material to PlantSteel tubes, reinforcement cages and concretePrecast concrete piles unless manufactured on siteStone
Construction — Materials storageTube and cage lay down areaPrecast pile lay down / curing areaStone stockpiles
Construction — NoiseYes if top driven but limited if bottom drivenYesMachine only
Construction — VibrationYesYesYes
Construction — SpoilNone, but ground heave possibleNone, but ground heave possible20 - 100% Nett volume
Construction — OtherPredrilling can be used to overcome obstructions. Enlarged bases can be formed to enhance capacityVariable pile founding depth can lead to high wastage levels and jointing expensiveTop feed “Wet” process requires water circulation system and settlement ponds to contain silts
Sheet Pile Wall
Secant Pile Wall
Diaphragm Wall
AdvantagesSheet piles are best suited for the following applications: temporary retaining walls, cofferdams and other temporary structuresThis is a permanent solution which provides increased wall stiffness compared to sheet pilesDiaphragm walls tend to be used for retaining very deep excavations as they can be designed to take very high structural loads
MethodologyClutched sheet piles driven into position.A series of piles installed so that they overlap to form a wall.A series of interlocking reinforced concrete panels.
Construction — EstablishmentCranes, vibros and hammers and / or pile jacking plant50-60T self erecting hydraulic drilling rigs and handling crane.50T crane + grab, handling crane, mud conditioning plant, mud storage
Construction — Piling productivity16m deep - 600mm wide sheet piles @ 22No/day (in clay or sand materials)16m deep - 600dia @ 4No/day in soft material including a 3m soft rock socket depth16m deep by 800mm wide @ 14-40m3/day of completed wall per rig per day
Construction — Materials to siteSheet PilesConcrete, reinforcement cagesBentonite, reinforcement cages or concrete panels
Construction — Work face accessPlant & Materials deliveryPlant & Materials deliveryPlant materials and pipelines for mud circulation
Construction — NoiseYes, unless jacked inMachine onlyMachine only
Construction — VibrationYes, unless jacked inNoNo
Construction — SpoilNo100% nett volume100% nett volume
Product — Wall MovementFlexible, can be increased with clutched king piles. More props or anchors can be used to reduce movementsIn-situ wall with ground supported throughout construction. Very stiff.Ground supported throughout excavation. Stiffest option given wall thickness
Product — WatertightnessGood with joint treatmentGroundwater control over pile length and satisfactory performance with some seepagesExcellent over full depth of the wall with waterbar across panel joints.
Product — ConnectionsWelded below capping beam levelDrilled & grouted bars into piles, shear & bending capacity possibleFull moment & shear connection via box-out and pull-out bars
Product — DurabilityInternal painting and sacrificial thickness of steelConventional concrete in the ground design. Internal lining for long-term seepageConventional concrete in the ground design. No internal lining necessary
Product — Load CapacityLow end bearing capacityCapacity can be enhanced by increasing the length of pilesWall has a large bearing area and individual panels can be extended
Soldier Pile Wall
Bored Pile Wall
Soilmix/Slurry Wall
AdvantagesSoldier pile and lagging walls are the most inexpensive systems compared to other retaining walls. They are also very easy and fast to constructLow cost and speed of construction for temporary and permanent retaining walls and soil supportExcellent resistance to contaminated groundwater. They have ability to adapt to ground movements such as earthquakes
MethodologyConstructed using piles timber infill panels (timber, steel or concrete)Series of bored piles installed relatively close together with shotcrete archesSteel or precast concrete elements placed in fluid soilmix / slurry
Construction — Establishment50-60T self erecting hydraulic drilling rigs and handling crane50-60T self erecting hydraulic drilling rigs, handling crane and concrete pumps50T crane + grab / CSM, handling crane / grout plant with screw feed silos, high pressure pumps
Construction — Piling productivity16m deep - 300mm square piles @ 18No/day16m deep - 600dia @ 4No/day in soft material including a 3m soft rock socket depth16m deep by 800mm wide @ 20-50m3/day of completed wall per rig per day
Construction — Materials to siteConcrete, reinforcement cages, steel or precast concrete panelsConcrete, reinforcement cagesCement, bentonite, steel or precast concrete panels
Construction — Work face accessPlant & Materials deliveryPlant & Materials deliveryPlant, materials and pipeline delivery of slurry
Construction — NoiseYes, if driven sectionsMachine onlyMachine only
Construction — VibrationYes, if driven sectionsNoNo
Construction — SpoilDependant on installation method100% nett volume30%-80% Nett volume
Product — Wall MovementGround unsupported allowing relaxation prior placement of panels and backfilling. Stiffness depends on structural section and backfill compactionGround unsupported allowing relaxation prior to concrete. Finished product stiffGround supported with stiffness dependant on steel section. Precast panels can increase stiffness.
Product — WatertightnessPermeable with no groundwater control below excavation. Seepages long termPermeable until shotcrete in place with no groundwater control below. Seepages long termGood temporary performance due to replacement with CB slurry but some seepages
Product — ConnectionsNumerous connection options dependant on materials usedDrilled and grouted bars into piles, shear and bending capacity possibleWelded to steel sections, shear & bending capacity possible.
Product — DurabilityConventional concrete in the ground design or sacrificial steel thickness given long term seepage potentialConventional concrete in ground designSacrificial thickness of steel and internal lining wall for long-term groundwater seepage
Product — Load CapacityCapacity can be enhanced by increasing the length of piles.Capacity can be enhanced by increasing the length of some piles.Capacity limited by penetration of steel beams
Last updated on