Pile Installation Productivity







Number of bored pile that can be installed per day

Pile diameter, or pile width, or sheet pile width
m
Pile length
m
Geotechnical conditions - SPT (N-value x 2) - blows/300mm **
kPa
Socket material strength of socket UCS(MPa) *
MPa
Engine (kw) or vibro weight(t) x 25
kw

Production rates relative to piling methodologyValueUnitConcreteUnit
Bored Piles0no/shift0m3/day
Bored Piles with Casings0no/shift0m3/day
CFA Bored Piles0no/shift0m3/day
Driven H Piles0no/shift
Driven Tubes Piles with shoe0no/shift
Precast Concrete Piles0no/shift
Vibro Replacement0no/shift
Sheet Pile Wall0no/shift
Secant Pile Wall0no/shift0m3/day
Diaphragm Wall30-50m3/shift30-50m3/day
Soldier Pile Wall0no/shift
Contiguous Pile Wall0no/shift0m3/day
Soil Mix/Slurry Wall100-160m3/shift100-160m3/day

References:

  1. 1. ** Course materials = SPT N-value (blows/300mm) x2 or fine materials = Cohesive strength (kPa)
  2. 2. * Rock - Unconfined uniaxial compressive strength qu (MPa)
  3. 3. It's important to match the piling equipment with the task at hand. See Splicing man-hours.